Clubhouse History
First ideas on location in 2003. Notice how we ended up building it around the redwood tree in the left side of this photo.
Poured 100 + cu. yds of concrete for the foundation in November of 2007
120 Tons of Logs delivered May of 2008. They were offloaded out at the Santa Lucia Preserve's maintenenace yard, then I had to shuttle them in on a smaller truck (pictured on the left) down our road.
After being delayed a month from the Basin Fire, We started to layout logs in late July '08
One weeks progress
One months progress, late August 08
Roof taking shape
Mid October 08
waiting for sprinklers to be installed, November
Waiting for the thaw... late December 08.
January...Still waiting... but in the meantime were installing the log siding on the left portion.
by the spring the fireplace was taking shape.
The metal roof was completed in March
by early summer the exterior was really taking shape
This shot from early July shows the progress of the stone columns
In preparation of moving the old changing rooms, a new foundation was poured
By Mid September '09 the front columns were complete
and the changing rooms have been moved!